Construction Updates
Progress Photo as of December 29, 2006

39.38% complete, 44 days ahead of the Overall Work Schedule
Schedule of topping off is on 31 March 2007
1,140,000 safe man hours reached last 29 December2006
Structural Works up to 34th Floor
Masonry Works from Ground Floor up to 28th Floor
Exterior Wall poured up to 23rd Floor