Construction Updates
Progress Photo as of November 25, 2006


33.87% complete, 42 days ahead of the Overall Work Schedule
Schedule of topping off is on 31 March 2007
960,000 safe man hours reached last 25 November2006
Structural Works up to 29th Floor
Masonry Works up to 19th Floor, 21st Floor
Exterior Wall poured up to 21st Floor