Construction Updates

Construction progress photo as of December 11, 2006






Overall project accomplishment is 92.48%
Architectural works on – going at 25th to 27th Floors
Glass works is almost complete - 90%
Structural works is 100% completed, on – going Escallator Installation and High-Rise Elevator
Parking Elevator installed, on-going Architectural works @ Lobby
Fit – out works (by tenant) is also on – going

 

 

 

 