Construction Updates
Construction progress photo as of February 19, 2007

Overall project accomplishment is 97.90%
Architectural works completed up to 27th Floors
Glass works is complete - 100%
Structural works is 100% completed, on going works are Escalator cladding and Elevator testing
Parking Elevator and Architectural works @ Lobby-completed
Fit – out works (19th to 22nd Floor)
Click here to view Robinsons Cybergate Tower 2 Project Profile
|