Construction Updates
Construction progress photo as of November 26, 2006

Overall project accomplishment is 90.62%
Architectural works on – going at 26th to 27th Floors
Glass works is on – going at 27th Floor
Structural works is 100% completed, on – going Escallator Installation and High-Rise Elevator
Parking Elevator installed, on-going Architectural works @ Lobby
Fit – out works (by tenant) is also on – going