Construction progress photo as of October 30, 2006

Overall project accomplishment is 86.65%
Architectural works on – going at 19th to 25th Floor
Glass works is on – going at 25th Floor
Structural works is 100% complete, on – going Waterproofing works at Roof Deck
Parking Elevator installed, on-going installation of Passenger Elevator 3
Fit – out works (by tenant) from 10th to 17th floor is also on – going