Construction Updates
Construction progress photo as of September 15, 2006

Overall project accomplishment is 79.91%
Architectural works on – going at Ground Floor, 6th, 16th to 22nd floor
Glass works is on – going at 20th & 21st floor
Structural works is 87.25% complete, on – going concreting at Machine Room
Low rise passenger elevator 1, 2 and 4 is working
Fit – out works (by tenant) from 10th to 17th floor is also on – going